Production Scheduling supports the following precedence relationships:
NameDiagram LabelDescription
Starts After EndS>EOne operation starts after the end of the previous operation, according to the time intervals displayed in the Minimum and Maximum separation fields.
Starts At EndS@EOne operation starts at the exact end of the previous operation.
Starts After StartS>SOne operation starts after the start of the previous operation, according to the time intervals displayed in the Minimum and Maximum separation fields.
Starts At StartS@SOne operation starts at the same time as the other operation.
Ends At EndE@EOne operation ends at the same time as the end of the other operation.
Minimum or Maximum+When S>S or S>E, indicates that the precedence relationship has a minimum or maximum separation.